Installation guide
15
(2) Mounting the drainpipe
Process photo Work details
Things to obey
(installer)
Items to check
(manager)
Fix the
drainpipe in the
channel or
hanger.
A group of two person
should work on the pipe
(not using excessive
force).
Check the channel/hanger
fixing intervals (1.5m or
less)
(3) Checking the drain slope
Process photo Work details
Things to obey
(installer)
Items to check
(manager)
Checking the
gradients.
Obtain good slope to
facilitate smooth drainage
of the condensed water.
(1/100)
Check the slope.
(4) Pipe connection
Process photo Work details
Things to obey
(installer)
Items to check
(manager)
Connect the
pipes only if
there is no
leakage.
(Drainpipe in
each region)
Apply sufficient bond to
the pipe.
- Do not perform in the
winter season.
- Use Standard Quality
bond.
(5) Pipe connection and socket works on the indoor unit side
Process photo Work details
Things to obey
(installer)
Items to check (manager)
Use the
drainpipe
components for
the location that
the indoor unit
is connected to.
Check the height and
maintain the drain slope
while performing the
work.
Check the height.
Seitenansicht 14